A large Mechanical & Electrical project was undertaken at the Priory School during the school holidays summer recess.

R L Crafter & Co Ltd carried out both M&E installations which included for the following: -

Mechanical.

  • Complete strip out and renewal of the main boiler plantroom, installing new 1000Kw boilers
  • New steel welded distribution pipework to 10” diameter
  • Pressurisation unit and expansion vessels
  • Gas pipework and safety systems
  • CT and VT pipework circuits
  • BMS controls system and panel
  • Insulation
  • 1000 litres hot water calorifiers
  • Chemical treatments and power flushing of existing school heating systems

Electrical.

  • New classroom Power and Lighting circuits
  • New Light fitings
  • Distribution boards
  • Metering 
  • Testing and certification